Cables transfer electricity; their MW ratings are not generating capacity. EGL2 connects Peterhead to Drax. EGL1, EGL3, EGL4 and EGL5 have different endpoints and delivery stages.
InterconnectorsUnder construction
700 MW
Transfer capacity
Ireland / France · Ireland
EirGrid / RTE
Irish onshore cable installation and testing were reported complete in May 2026. Celtic connects Ireland directly to France. It is included as a neighbouring-market project relevant to all-island electricity trading; it is not a Great Britain grid connection.
Transmission linksUnder construction
2,000 MW
Transfer capacity
East Lothian / County Durham · United Kingdom
SP Energy Networks / National Grid
Onshore construction was announced in February 2025. EGL1 connects the Torness area to Hawthorn Pit over a predominantly subsea route of more than 190 km. It is distinct from EGL2 and does not terminate at Drax.
Transmission linksUnder construction
2,000 MW
Transfer capacity
Aberdeenshire / North Yorkshire · United Kingdom
SSEN Transmission / National Grid
EGL2 links Peterhead and Drax through a 505 km HVDC route. Construction is underway following the 2024 approvals. Its converters connect the subsea DC system to the AC transmission networks at each end. It transfers electricity between regions; its rating is not additional generating capacity.
Grid upgradesUnder construction
Not published
Component of a parent transmission project; no additional link capacity counted
Peterhead / Boddam, Aberdeenshire · Scotland
SSEN Transmission / National Grid (EGL2)
The Scottish terminal of the 2 GW, 525 kV Peterhead–Drax link is under construction near Boddam. It converts between AC and DC and connects to the Peterhead AC network. Hitachi Energy supplies converter technology with BAM delivering civil works. It is separate from the existing gas-fired Peterhead power station.
Grid upgradesUnder construction
Not published
Component of a parent transmission project; no additional link capacity counted
Peterhead / Boddam, Aberdeenshire · Scotland
SSEN Transmission / National Grid (EGL2)
EGL2’s Scottish landfall connects its subsea cable to the onshore route serving the Boddam converter. Horizontal directional drilling and cable landing are separate construction packages from the converter buildings. Prysmian is the EGL2 cable supplier; the NKT works at Rattray Head belong to a different link.
Grid upgradesUnder construction
Not published
Component of a parent transmission project; no additional link capacity counted
Drax / Wren Hall, North Yorkshire · England
SSEN Transmission / National Grid (EGL2)
Wren Hall is the English converter terminal of the 2 GW Peterhead–Drax link, adjacent to the Drax transmission connection. It converts electricity between the subsea DC system and the AC grid. The converter is separate from Drax’s generating units and proposed data centre.
Grid upgradesUnder construction
Not published
Component of a parent transmission project; no additional link capacity counted
Netherton / Longside / Peterhead, Aberdeenshire · Scotland
SSEN Transmission
The two AC substations at Netherton Hub support generation and storage connections and onward transmission. They form a different infrastructure package from the site’s HVDC converters. Shared site civil works are underway; detailed electrical approvals and energisation follow separately.
Grid upgradesUnder construction
Not published
Multiple substations and converters
Longside / Flushing / Peterhead, Aberdeenshire · Scotland
SSEN Transmission
Main hub construction is underway near Longside, west of Peterhead. The development comprises 400 kV and 132 kV substations, separate Spittal–Peterhead and EGL3 HVDC converter stations, a transmission hall identified for EGL5, and an operations and spares base. Shared site earthworks do not mean that every converter or cable is already operational.
InterconnectorsUnder construction
1,400 MW
Transfer capacity
Kent / Germany · United Kingdom
NeuConnect
Converter fit-out was reported in September 2026. NeuConnect is the first direct electricity connection between Great Britain and Germany, with approximately 725 km of land and subsea cables. It supports imports or exports according to system conditions.
Transmission linksUnder construction
220 MW
Transfer capacity
Orkney / Caithness · Scotland
SSEN Transmission
Underground cable installation began in September 2026. The scheme includes Finstown substation, a 14 km land cable to Warebeth and a 53 km subsea cable to Dounreay. It creates Orkney’s first connection to the mainland transmission network.
Grid upgradesUnder construction
Not published
AC transformer replacement and network reinforcement; no extra generating capacity
Peterhead / Boddam, Aberdeenshire · Scotland
SSEN Transmission
SSEN reports first-phase construction underway in July 2026, including platform earthworks, drainage and a SuDS pond. Balfour Beatty is carrying out the works. Construction is expected to finish by 2028, with commissioning and energisation by 2030. This is separate from the EGL2 HVDC converter and existing power station.
Transmission linksUnder construction
2,000 MW
Transfer capacity
Caithness / Rattray Head / Crimond / Longside / Peterhead · Scotland
SSEN Transmission; cable contractor NKT
Cable construction is underway. The approximately 203 km link includes a 166 km subsea section between Sinclair’s Bay and Rattray Head. It connects the Banniskirk and Netherton hubs and supports movement of northern Scottish generation toward demand centres.
Grid upgradesUnder construction
Not published
Component of a parent transmission project; no additional link capacity counted
Rattray Head / Crimond / Peterhead, Aberdeenshire · Scotland
SSEN Transmission
The Rattray Head landfall north of Peterhead serves the 2 GW Spittal–Peterhead cable, connecting onward to Netherton near Longside. NKT is the cable contractor; Nicol of Skene carries out local works. SSEN confirmed 1.7 km landfall HDD drilling underway in July 2026. This is distinct from EGL2’s Sandford Bay landfall.
Transmission linksEnabling works
1,800 MW
Transfer capacity
Lewis / Highlands · Scotland
SSEN Transmission
Mainland cable preparation and associated early works are underway in 2026. The link is designed to connect Lewis to the mainland and unlock island renewable generation. This 1.8 GW scheme supersedes the earlier 600 MW proposal. Work packages are at different stages.
Grid upgradesUnder construction
Not published
Network reinforcement
North Yorkshire · England
National Grid
Preparation began in autumn 2024 and main construction in early 2025. Yorkshire GREEN reinforces overhead lines and substations in North Yorkshire. It complements regional grid investment but is a separate project from the Peterhead–Drax cable.