United States › Grid › Interconnection queues › Mississippi
BATTERY STORAGE · SOUTHEASTBattery storage project 25RSC-013, Lowndes County
Battery storage project 25RSC-013, Lowndes County is a 200 MW battery storage request in interconnection study in the Southeast interconnection queue, in Lowndes County, Mississippi, connecting to Tennessee Valley Authority.
- PlanningQueued Aug 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Aug 2031 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25RSC-013
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Tennessee Valley Authority
- Connection point (POI)
- TVA'S LOWNDES, MS 500KV SUBSTATION
- Location
- Lowndes County, Mississippi
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 1 August 2025
- Proposed online date
- August 2031
Location
Marker shows the centre of Lowndes County; the queue data does not give exact sites.
Power plants in Mississippi · Transmission lines in Mississippi
Other requests in Lowndes County
- Gas project 569, Lowndes CountyGas · 620 MW · in study
- Other project 53, Lowndes CountyOther · 900 MW · built
- Other project 53Other · 900 MW · built
- Lone Oak Energy Center(Calpine)Gas · 813 MW · built
- Caledonia Generating (Cogentrix)Gas · 813 MW · built
- Other project 15, Lowndes CountyOther · 450 MW · built
- Other project 15Other · 450 MW · built
- Gas project 223, Lowndes CountyGas · 122 MW · built
- Solar project 341, Lowndes CountySolar · 100 MW · built
- Solar project 415, Lowndes CountySolar · 100 MW · built
- Solar project 377, Lowndes CountySolar · 100 MW · built
- Gas project 310, Lowndes CountyGas · 78.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem